Holme Valley Riverside Way Revamp

Reverse 20 years of neglect by improving the footpath surface and drainage, way marking throughout the route, vegetation management, installation and repair of steps, and a new section of boardwalk.

Loading...

Our Delivery Report

Funded on 08 July 2022 | Delivered on 31 March 2023

£23,902

RAISED

82

BACKERS

60

DAYS TO FUND

BIGGEST PLEDGE

Largest pledge from Garfield Weston Foundation

£10,000

From Garfield Weston Foundation

500

people have visited this project!

Project Image
Project Image
m<sup>2</sup> of public or community space improve

15500 m2 of public or community space improved

Full-time job protected

1 Full-time job protected

Project Image
Hours volunteering opportunities

160 Hours volunteering opportunities

People involved in project delivery

69 People involved in project delivery

Project Image
Sir George Martin Trust

Sir George Martin Trust donated £1,500

Project Image
EPIKS

EPIKS donated £50

Kirklees Council

Kirklees Council donated £4,000


River Holme Connections

The Latest from Holme Valley Riverside Way Revamp

We are proud to have completed the Phase 1 Riverside Way Revamp Project!

We have installed hundreds of waymarking disks along the whole length of the route (9.6 miles).

During the “Riverside Way Revamp” project we managed to carry out remedial work at 21 locations.These works included the installation of a new boardwalk at Thongsbridge, installation of 80 metres of flexipave (surfacing improvement) at Primrose Hill, installation of revetment board and stone surfacing at Holmfirth, installation of 9 new way marker posts (throughout the route), vegetation management (at a number of sites along the route) and the installation of a stone causeway at Thongsbridge.

We carried out 14 tasks with volunteers to help improve the route. A total of 69 people helped, and these volunteers contributed a total of 160 hours.