Our Delivery Report
Funded on 08 July 2022 | Delivered on 31 March 2023
£23,902
RAISED
82
BACKERS
60
DAYS TO FUND
BIGGEST PLEDGE
£10,000
From Garfield Weston Foundation
500
people have visited this project!
15500 m2 of public or community space improved
1 Full-time job protected
160 Hours volunteering opportunities
69 People involved in project delivery
Sir George Martin Trust donated £1,500
EPIKS donated £50
Kirklees Council donated £4,000
The Latest from Holme Valley Riverside Way Revamp
We are proud to have completed the Phase 1 Riverside Way Revamp Project!
We have installed hundreds of waymarking disks along the whole length of the route (9.6 miles).
During the “Riverside Way Revamp” project we managed to carry out remedial work at 21 locations.These works included the installation of a new boardwalk at Thongsbridge, installation of 80 metres of flexipave (surfacing improvement) at Primrose Hill, installation of revetment board and stone surfacing at Holmfirth, installation of 9 new way marker posts (throughout the route), vegetation management (at a number of sites along the route) and the installation of a stone causeway at Thongsbridge.
We carried out 14 tasks with volunteers to help improve the route. A total of 69 people helped, and these volunteers contributed a total of 160 hours.